Sorry to see the steep little climb being bypassed, although it should require less maintenance.

 

 

Work on Fish Eagle is completed.  See photo for the bypass of the steep little climb - that section now flows beautifully.  Spare a thought for the trail builders who had to dig and move all that soil by hand.   

 

Also started with work on Protea Alley, but had to stop further work on other sections until it rains again.    

post-4890-0-81499500-1433873642_thumb.jpg

Link to comment
Share on other sites

  • Replies 1.2k
  • Created
  • Last Reply

Top Posters In This Topic

Top Posters In This Topic

Thanks Dirtman

 

Has the entrance to Fish Eagle also seen a spade or 2?

 

 

That whole section (up to the rock) has been rebuilt.

Link to comment
Share on other sites

Great!

 

Hope the trail has time to settle this time before being atacked by an event bringing riders who cannot stay on the trail. ;)

Link to comment
Share on other sites

Work on Fish Eagle is completed.  See photo for the bypass of the steep little climb - that section now flows beautifully.  Spare a thought for the trail builders who had to dig and move all that soil by hand.   

 

Also started with work on Protea Alley, but had to stop further work on other sections until it rains again.    

Rode it this morning. Nice !!!!

Link to comment
Share on other sites

More maintenance was done this week after the rains - only sections that remain are the exit of Ribbok and then  Rooikat, Geelslang and Mongoose.  It is still too dry to work on the  sections on the green route- hopefully they can be done after the rain forecasted for mid next week.   

 

The team also did some work on the rock garden on Lizard - see photo (click on photo to see the bypass on the right) .  Riders now have the option to ride the rock garden or ride an easier option next to it.   

post-4890-0-13017300-1434657134_thumb.jpg

Edited by dirtman
Link to comment
Share on other sites

More maintenance was done this week after the rains - only sections that remain are the exit of Ribbok and then  Rooikat, Geelslang and Mongoose.  It is still too dry to work on the  sections on the green route- hopefully they can be done after the rain forecasted for mid next week.   

 

The team also did some work on the rock garden on Lizard - see photo (click on photo to see the bypass on the right) .  Riders now have the option to ride the rock garden or ride an easier option next to it.   

 

Thanks Dirtman

 

A fast hard line (A) with a slower easier line (B) I understand, but a rock garden with a smooth bypass!?? :eek:

Are the MTBers getting soft or what? :devil:

Link to comment
Share on other sites

More maintenance was done this week after the rains - only sections that remain are the exit of Ribbok and then  Rooikat, Geelslang and Mongoose.  It is still too dry to work on the  sections on the green route- hopefully they can be done after the rain forecasted for mid next week.   

 

The team also did some work on the rock garden on Lizard - see photo (click on photo to see the bypass on the right) .  Riders now have the option to ride the rock garden or ride an easier option next to it.   

 

Looking good! Thanks man!

Link to comment
Share on other sites

Morning

 

Will there be half year permits for botties?

 

Yes, hoping to have them available at all sales points from saturday (27th). 

Link to comment
Share on other sites

Yes, hoping to have them available at all sales points from saturday (27th). 

 

 

Price?

Link to comment
Share on other sites

Create an account or sign in to comment

You need to be a member in order to leave a comment

Create an account

Sign up for a new account. It's easy!

Register a new account

Sign in

Already have an account? Sign in here.

Sign In Now
Settings My Forum Content My Followed Content Forum Settings Ad Messages My Ads My Favourites My Saved Alerts My Pay Deals Help Logout